PROJECT

YOHO DEVELOPMENT PROJECT – 2004

CLIENTS

SCOPE OF WORK

Detailed Design Stage

  • Transportation Analysis of deck YP
  • Deck loaded and fastened on top of cargo barge S45
  • The whole ensemble is loaded on top of the Blue Marlin vessel in Piggy Back configuration
  • Strength and fatigue analysis of the deck YP
  • Transportation analysis of the deck YQ (YQ) and the living quarters (LQ) on board the cargo barge BOA28, including stability check, extreme motions and minimum bollard pull analyses

SPECIFICS

  • The deck is restrained by means of skid shoes and diagonal tiedowns
  • The two vessels are modeled structurally to account for flexibility
  • The S45 barge is restrained to the Blue Marlin using springs in the vertical direction along with horizontal springs located at the transverse bulkheads