PROJECT

AZERI CENTRAL EAST PROJECT – 2019-2023

CLIENTS

bpsubsea e

SCOPE OF WORK

Installation Engineering Stage

  • Independant modelling of launch barge, crane vessel, jacket and topside
  • Jacket and Topside transport stability and motion analyses
  • Jacket launch simulations
  • Jacket docking procedure design, static and dynamic simulations
  • Jacket on-bottom stability analyses
  • Skirt Pile, upending, lifting and impact analyses during installation
  • Floatation Tank removal and towing analyses
  • Topside float-over and mating analyses
  • Mooring analyses prior to mating
  • Advise operational procedures

SPECIFICS

  • Caspian Sea in 137 m water depth
  • 8 legs, 15000 mT Jacket
  • 2 massive Floatation Tanks
  • 21000 mT Topside
  • Transportation and launch with STB-1 barge
  • Lifting with DBA Crane vessel
    Done in partnership with ORCA-OFFSHORE