YME FIELD – MOPU INSTALLATION PROJECT – 2008
CLIENTS
SCOPE OF WORK
Installation Design
- Design the installation steps to assemble the MOPU (11785 T) to the gravity base
- Simulation of the positionning of the MOPU above the base
- Lowering of the legs into the sleeves
SPECIFICS
- Time domain simulations
- The tugs are modeled as independant bodies connected to the MOPU with towwing lines and anchored to the ground by mean of mooring lines
- MOPU legs are connected to the sleeves by mean of non-linear gap connectors
- Several stages are studied from approaching the sleeves to full insertion of the legs