PROJECT
KUITO FPSO INSTALLATION PROJECT – 2002
CLIENT
SCOPE OF WORK
Basic Design Stage
- Lifting of a module on top of KUITO FPSO using Castoro 8 crane barge
- Mooring design of the Castoro 8 alongside the FPSO. Check of offsets to validate the use of a gangway between the 2 vessels
- Dynamic lift simulation to verify the impact loads from the module on the deck of the FPSO, for bumpers and lifting guides design
SPECIFICS
- The model includes 3 bodies and connectors of different stiffnesses
- Time domain simulations
- Outputs are connector loads, relative motions between points of different bodies (gangway ends, module supports and FPSO deck), velocities and accelerations of concerned points